Kerbside & Pole Mounted EV Charging

Australia's residential streets are already lined with power poles. Kerbside and pole-mounted EV charging puts that existing infrastructure to work, delivering public charging exactly where it is needed most; in high-density streets where residents park on the road and have no way to charge at home. EVSE delivers these projects end to end: site assessment, network approvals, hardware supply, licensed installation, and ongoing operation through the Exploren platform.

What is kerbside and pole-mounted EV charging?

Pole-mounted EV charging mounts a charging unit directly onto an existing power pole, connected to the overhead electricity network. Because the power is already at the pole, there is no need for trenching, new civil works or a separate grid connection – which makes it faster and considerably cheaper to deploy than a standard ground-up charging installation.

Kerbside charging is the broader category: any publicly accessible charger installed at the street edge, whether pole-mounted or on a pedestal. Both serve the same purpose – giving drivers without off-street parking somewhere reliable to charge closer to home.

Why Councils and Networks choose pole mounted charging 

Uses infrastructure you already have

Mounting to an existing pole avoids the civil works, trenching and new grid connection that drive most of the cost in public charging projects.

Serves the residents who need it most

Households without a driveway or garage cannot install a home charger. Kerbside charging is the only practical way to give those residents reliable access.

Scales one pole at a time

You are not committing to a large single build. Sites can be added progressively as demand grows, spreading cost across budget cycles.

Runs itself once installed

Chargers are monitored 24/7 through Exploren, with remote diagnostics, adjustable tariffs and full session reporting - so your team is not managing hardware day to day.

Built for the street

Ocular hardware is housed in heavy-duty metallic casing rated for Australian conditions and exposed public locations.

Technical Specifications

Specification
Ocular IQ Commercial
Ocular IQ Dual Commercial
Ocular DC Titan
Type
AC, single port
AC, dual port
DC, single port
Output
7kW single phase / 22kW three phase
Multiphase 7/22kW, single & three-phase
40kW
Connection
Universal (socket) or tethered
Socketed
5m cables
Display
7" LCD
7" LCD
7" Touchscreen
Protection
IP54
IP55, IK10
IP55, IP65
Operating temp
-40°C to +75°C
-30°C to +50°C
-30°C to +50°C
Dimensions (H x W x D mm)
400 x 270 x 130 mm
550 x 320 x 177 mm
670 x 690 x 325 mm
Weight
10-14kg
18.5kg
93kg
Mounting
Wall or post mounted
Wall or post mounted
Wall or floor via optional pedestal
OCPP
1.6J, 2.0
1.6J, 2.0
1.6J, 2.0

How a kerbside charging project runs

Kerbside charging projects are rarely held upby the hardware or the installation. The time sits in the approvals and knowing the pathway that is most of what we bring to a project. Here’s how a typical rollout runs

Stage 1 - Site selection and assessment

We assess sites alongside the installing electrician. The first priority is utilisation: chargers near shops, cafes and other amenities get used, and a well-used charger is what makes a site worth building. On side we confirm where the charging station can go, where mechanical protection needs to sit, and the safety conditions for both the construction work and the drivers who will use the bay once its live.

Stage 2 - Council approval and community consultation

Every council sets its own criteria, so this stage takes its shape from who you are. On our Inner West Council project it meant local consultation with residents near each charging location, traffic management approval, and Section 138 and 139 deeds for construction. Whether a development application is needed varies by state. This is the stage to start early. It is consistently the longest and least predictable part of a kerbside project.

Stage 3 - DNSP approval

Once council approval is in place, the power supply must be approved by the local network provider. Requirements vary between networks so we confirm the pathway for your specific DNSP at the outset rather than assuming it will mirror another region.

Stage 4 - Metering and retailer setup

The energy retailer assigns NMIs to the metering provider, and the meter is installed on site. It is an easy stage to underestimate: it involves several parties who each work to their own timeframes, so it needs actively managing rather than waiting on.

Stage 5 - Construction

Once approvals are cleared, construction moves quickly - around two weeks per site. We establish an exclusive zone so the public cannot access the work area, take power from the pole and run it down, excavate through to the switchboard and charger positions, then backfill and install mechanical protection such as bollards and signage.

Stage 6 - Live and operating

Chargers come online through Exploren. Drivers start by scanning a QR code, while you set tariffs and access levels and pull reporting on usage, duration and energy delivered.

Where the time actually goes:

Approvals dominate the timeline. On the Inner West Council project, it took 8-12 months from first engagement to approval to install – against roughly two weeks of construction. The most common causes of delay are council decision cycles including election periods, traffic engineers seeking design changes, and community objection to proposed charger locations. Engaging early, and consulting residents before designs are locked in, is what shortens it.

DNSP (Distribution Network Service Provider) approval timeframes can vary and take time to process. We recommend contacting EVSE as early as possible in your planning to get the ball rolling.

 

Inner West Council: 22 Kerbside Charging Sites, Built Around the Grid

Challenge

Inner West Council set out to expand public charging for residents without access to home charging. The limiting factor was never the ambition – it was the grid. The council needed to fit meaningful charger numbers into existing electrical infrastructure without overloading it.

Solution

EVSE assessed the council’s existing electrical infrastructure and designed a solution that maximised charger numbers within the capacity available. The rollout delivered 22 kerbside charging sites: 23 Ocular IQ Dual Port Towers and one Ocular DC Titan, downrated to 80A to align with grid capacity while still delivering fast charging. Sites were distributed strategically across the council area for both residents and visitors.

Results

The network runs on Exploren software. Drivers scan a QR code to start charging. The council sets and adjusts tariffs, billing by charging duration, and pulls session data on usage, duration and energy consumed – so decisions about where to expand next are based on real behaviour, not guesswork. Because the network is built to scale, the council can add sites as EV uptake grows without redesigning what is already in the ground.

Keep your communities happy

Easy to use, simple to manage software

With our streamlined billing system, managing access and usage has never been easier. You can incentivise EV charging with flexible, adjustable tariffs, empowering you to offer tailored solutions. Our automated, on-demand reports give you complete visibility into charging sessions and key data, allowing you to optimise charging based on user needs.

Powered by Exploren software, your chargers are automatically monitored 24/7. Any issues are resolved quickly and remotely, ensuring your charging stations are always ready to go – because no one wants to deal with a charger that’s out of service.

Prepare for the future now.

EV uptake is growing fastest in the suburbs where residents have the least access to charging. Every year that kerbside infrastructure lags behind, the gap widens between drivers who can charge at home and those who cannot. Building street-level capacity now – progressively, pole by pole – means being ready for demand rather than reacting to it.

Reliable, future-proof & scalable infrastructure

Dynamic load management avoids the need for costly upgrades using the energy infrastructure, saving you money and utilising the available resources for more charging stations.

Our smart charging solutions are designed to be continuously installed over time, making installing multiple charge points super cost-effective.

 

FAQs

A pole-mounted EV charger is a charging unit fixed directly to an existing electricity power pole and connected to the overhead network. Because power is already present at the pole, installation avoids the trenching, civil works and separate grid connection required by conventional public charging installations.
Kerbside charging is designed for drivers who have no off-street parking — residents of apartments, terraces, townhouses and older strata buildings who cannot install a charger at home. It is typically delivered by local councils, network operators and charge point operators working in partnership.
Most kerbside chargers are AC units at 7kW or 22kW. As a general guide, a 7kW charger adds roughly 40–50km of range per hour and a 22kW charger roughly 120–140km per hour, though actual speed depends on what your vehicle's onboard charger can accept. DC options are available where a site needs faster turnaround.
This is set by the commercial model agreed for each project. EVSE offers full turnkey delivery where you own and operate the assets with our support, as well as Charging as a Service arrangements. Chargers are monitored 24/7 through Exploren, with issues diagnosed and resolved remotely wherever possible.
Drivers scan the QR code on the charger and start a session through the Exploren app. Site owners can set and adjust tariffs, control access levels, and pull reporting on session duration, energy delivered and usage patterns.
Grant funding may be available, depending on which state you reside. Check out our EV charging incentives page to learn more.
Approvals, not construction, set the timeline. Construction on a cleared site takes around two weeks. Council approval and community consultation is the longest and most variable stage. On our Inner West Council project it took 8-12months from the first engagement to approval to install. Timeframes differ by council and by DNSP, which is why we recommend engaging at the earliest stage of your planning.
It depends on the state and the council. On our Inner West project the works were DA exempt, with approval instead granted through Section 138 and 139 deeds under the Roads Act, alongside traffic management approval and community consultation. Other council and states set different requirements. We confirm the approval pathway for your specific site before any design works begin.

Contact us for all Electric Vehicle Charging
Solutions and Accessories Across Australia
& New Zealand.

EVSE believes in a green sustainable future by delivering the latest EV Charging technology at the lowest price. All our work is certified and guaranteed with the backing of global brands.

Our team of experts can provide specialist EVSE advice and are available to answer any of your questions over the phone

"*" indicates required fields

Find the right charger

Tell us about your car and home to see recommendations.

Get the best price

Stocking the best Electric Car products from the World’s leading brands.

Reliability

All of our EVSE products are compliant with Australian & International standards.